Filling In Posted on August 1, 2018 Posted in Building- Phase 2 Progress Demolition completing on existing building Interior framing nearing completion Roof ridge cap nearing completion HVAC rough in continues Exterior sheathing and Tyvek complete west side Exterior sheathing complete north wall