Category: Building- Phase 2 Progress

Filling In

Demolition completing on existing building Interior framing nearing completion Roof ridge cap nearing completion HVAC rough in continues Exterior sheathing and Tyvek complete west side Exterior sheathing complete north wall

Made in the Shade

The roof is going up and things are really taking shape on the inside! Roofing Panels Installation Connection of New Building to Existing Building Classrooms Left, Restrooms and AWANA Beyond on Right Exterior Sheathing on Back Wall Start of Center

Framed

Final Pieces of Rigid Frame Assembled Readying for Cables that Support Roof Insulation Installing Support Cabling Final Pieces of Roof Purlins Installed Start of Center Section of Roof Structure Support Cabling Installation

Taking Shape

A great amount of progress took place last week even as VBS went on both in front of and inside the building. The structure is taking shape!

Vertical Momentum

 The frame is going up on Phase 2!

Aerial Shots

Thanks to Paul Conn for these excellent aerial photos of the current status of Phase 2 construction!

Foundation Preparations

Digging grade beams. Forms set in place. 8” fire line work. Fire line work. Electrical panels installed. Corner of grade beam at pier location.

Piers Will Be Going in Soon

Concrete Subcontractor Shooting Gridlines Receiving Rebar Steel and Ties for Piers Tying Cages Up to the Sky Up to the Sky

Surveying & Service Panel

Surveying and Establishing Final Grade – 3/9/18: Receiving New Electrical Service Panel – 4/11/18:

Aerial Photos

Here’s a look at the current status of the building project from up above. Thanks to Paul Conn for these drone photos!

Top